Location: Milpitas, CA
General Contractor: Oltmans Construction
Project Features: Tilt-up structure based in Milpitas, CA that consisted of 385,000 SF slab on grade placement completed in 6 pours. The entire project was completed in 18 weeks from start of foundations to completion of the panel closure. The duration included installation of site panels.